Subject: RSHS Stage Wall Project Change Orders
Board Goals:
Enclosure Change Orders: RSHS Stage Wall Project
File Attachment:
Change Orders RSHS Stage Wall Project.pdf
Background & Rationale: Change Order Dated 5-29-19: Expanded testing due to expanded wall construction. $3,582.50
Change Order Dated 4-16-10: Existing doors replaced as they would not fit in the new door frames of the new wall. $5,079.00
Budget to be Charged: Contingency
Motion: Consent Agenda