Meeting Date:
|
7/9/2018 - 6:30 PM
|
Category:
|
New Business
|
Type:
|
Action
|
Subject:
|
Purchase of EMC Storage Maintenance and Support
|
Board Goals:
|
7. 2018-2019, 17-18, 16-17, 15-16, 14-15 & 13-14: Support the implementation of the approved four-year technology plan Support the implementation of the approved two-year technology plan for effective classroom delivery including the use of virtual technology and social networking.
|
Enclosure
|
|
File Attachment:
|
|
Background & Rationale:
|
The district's EMC server storage hardware is due for maintenance and support. A bid was released and Sirius returned the only bid at an annual cost of $97,232.97. The district went to market and obtained pricing directly from EMC and 2 other vendors (CDWG & Pomeroy) which was consistent with this bid. The district has selected to purchase maintenance and support through Sirius at an annual cost of $97,232.97.
|
Budget to be Charged:
|
Technology budget
|
Motion:
|
I move that the Board authorize the purchase of EMC maintenance and support through Sirius in the amount of $97,232.97.
|
Approvals:
|
Recommended By:
|
Signed By:
|
|
Melissa Tebbenkamp - Director of Instructional Technology
|
|
Signed By:
|
|
Dr. Steve Shelton - Associate Superintendent of Operations
|
|
Signed By:
|
|
Dr. Allan Markley - Superintendent
|
|
|
|
|
|
|
|